Adjudication enforcement - What impact will Bellway Homes Ltd v Surgo Construction Limited have on interim payment disputes?
April 18, 2024
Adjudication enforcement - What impact will Bellway Homes Ltd v Surgo Construction Limited have on interim payment disputes?April 18, 2024 The recent case of Bellway Homes Ltd v Surgo Construction Limited1 (England and Wales) has attracted a great deal of commentary in the legal press, mainly because it appears to be the first adjudication enforcement decision which considers whether a ‘smash and grab’ and a ‘true value’ claim can be referred to adjudication as one dispute (the answer is, yes!).
However, it also raises an interesting point regarding the interplay between the mandatory payment provisions incorporated into construction contracts by the Housing Grants, Construction and Regeneration Act 1996 (as amended) (the “Construction Act”) and the jurisdiction of an adjudicator to award payment in an adjudication where none may be due in accordance with those provisions.
In this particular dispute, the sub-contractor’s smash and grab claim failed for want of a notified sum under section 111(2) of the Construction Act, but the adjudicator went on to value the sub-contractor’s account and found payment was due. It raises the issue - as the Construction Act requires there to be a notified sum, if there isn’t one, how does payment fall due? On enforcement, the TCC upheld the adjudicator’s decision.
In this article, we look at the significant impact that this judgment could have on future interim payment disputes in the construction industry.
The disputeBellway Homes Ltd (“Bellway”) was the Employer and Surgo Construction Limited (“Surgo”) was appointed as the Main Contractor on a residential housing development.
Surgo sub-contracted part of its works relating to the installation of kitchens to Roundel Manufacturing Limited (“Roundel”). Roundel made an interim application on 22 December 2022 for payment of £152,225.23 (the “Application”). Surgo did not issue any payment notice or payless notice and did not make payment. Roundel referred the matter to adjudication and asked the adjudicator to decide:
The adjudicator found that Roundel’s application for payment was not valid and that it comprised: “no more than a than a number of accountancy summaries that do not seem to correlate with each other.” It therefore did not meet the test under the Construction Act of being valid for the purpose of a ‘smash and grab’ adjudication. On the alternative declaration, the adjudicator concluded that Surgo had instructed the works for which Roundel sought payment and therefore valued the account on the basis of the invoices which Roundel had issued when it completed the installation of each kitchen.The adjudicator decided that Surgo owed Roundel the sum of £146,118.82 for the true value of the works. Surgo refused to make payment. Roundel assigned its claim to Bellway and Bellway brought enforcement proceedings. Surgo resisted enforcement on the basis that:
In response, Bellway contended there was only one dispute – what sums were due arising out of Roundel’s application for payment? There were two routes to answering that question – smash and grab or the true value of the works. Further, Bellway argued that the adjudicator was simply answering the question being asked - what amount was Roundel due up to the end of December 2022 calculated on a substantive basis? If this was wrong in law, that was not relevant to the enforcement proceedings. What did the Court decide?The adjudicator had jurisdiction to determine the dispute. The Judge found that this could be described as a single dispute in respect of a sum due and the notice of adjudication: “clearly characterised the dispute as a failure to pay any sum due to the Claimant by the final date for payment, whether by means of a notified sum or by way of a substantive amount due”. To characterise this as two different disputes would be taking a ‘too legalistic’ approach. The Judge therefore agreed with Bellway that “the character of this matter is that there are two routes advanced to the same goal of determining a sum owned”. On exceeding jurisdiction, the Judge was of the view that Surgo’s position: “does not stand up to close scrutiny”. The adjudicator’s discussion of the application’s validity did not mean he was rejecting the payment application as capable of being an application for payment in any circumstances. The alternative claim advanced by Roundel in the adjudication was simply introducing an alternative route to the adjudicator’s decision, namely a request for a true value adjudication if the default payment provision basis failed. The Judge therefore rejected both of Surgo’s arguments and upheld the decision. What impact might this judgment have on future disputes?Whilst there are a number of legal authorities which have grappled with the issue of single or multiple disputes, this is the first which concerns the different routes to payment. As matters stand, where a party is asking an adjudicator what sum is due, if worded appropriately, the same adjudication can consider the arguments on a default payment/smash and grab and true value basis and such approach is not likely to be considered two separate disputes. This is significant, as it paves the way for referring parties to frame their claims for sums due on an alternative basis, which should save time and money and avoid the need for the parties to engage in serial adjudications. However, the inevitable effect on the responding party is that they will have to defend a claim on both basis in a very short time period, which will obviously have cost implications and could increase breach of natural justice challenges. It also raises issues regarding the viability of future true value claims – if the responding party puts forward its position on the true value in defence, it may be precluded from bringing its own ‘true value’ adjudication in the future on grounds that it is the “same or substantially the same” dispute being referred to adjudication again (paragraph 9 of the Scheme). In reality, it may be that there are limited circumstances where a referring party (a payee, in this case) seeks a true value decision in the alternative because a payee would usually be the party bringing a smash and grab claim to avoid or delay a true value claim until it receives cash in its pocket. In any event, it will be interesting to see what an adjudicator will do where it is asked to consider both alternative claims, but the smash and grab/default payment basis is valid and successful – will the adjudicator put forward a true value in the alternative in any event? Presumably the immediate payment obligation under statute will prevail in these circumstances, particularly given the intention of the Construction Act to aid cash flow and the ‘pay now, argue later’ maxim? Or, is a decision based on the true value of the works beneficial (and commercially sensible) for all parties in the long run? These questions remain unanswered for now, so it seems to be a case of watch this space! It also seems likely that there will be future enforcement decisions which consider these issues and the interplay between smash and grab and true value adjudications. Key takeawaysThis decision serves as a reminder that:
What else do I need to know?This decision indicates that the ‘true value’ of the works can still be established where there is no ‘notified sum’ pursuant to section 111 of the Construction Act. So, does this mean that there does not need to be a notified sum for an adjudicator to be able to award payment? It is not clear that this will be the case when considering interim payment disputes in the future. First, this was an enforcement decision and the Court’s approach is to generally uphold the decisions of an adjudicator (in the absence of a valid jurisdictional challenge), even where there may be an error of law. Secondly, there was no Part 8 claim to seek a final determination of the issue or challenge the decision on the basis that it was legally incorrect. The outcome may have been different in these circumstances. What it does show is that non-compliant applications for payment are still capable of being assessed in a payment dispute when referred to adjudication.
Latest Insights
Latest News
Latest Events
legal updates June 03, 2026 UK Government confirms refinements to CfD allocation round 8 legal updates June 02, 2026 UK Retail Finance Horizon Scanner - May 2026 legal updates June 02, 2026 Employer contributions to the Teachers' Pension Scheme (TPS) set to ease fo... legal updates June 01, 2026 UK: Reform of the Consumer Credit Act 1974 takes shape client news June 02, 2026 Next stop, public ownership: Eversheds Sutherland advises DfT on GTR transi... firm news June 01, 2026 Eversheds Sutherland strengthens restructuring offering with senior partner... firm news June 01, 2026 Eversheds Sutherland strengthens Commercial Advisory practice with technolo... client news May 28, 2026 Eversheds Sutherland advises Schroders Greencoat on acquisition of Dutch bi... virtual Education Webinar - Legal refresher for education institutions – governance... June 04, 2026 11:00AM - 12:00PM virtual UK employment law training June 09, 2026 1pm - 4pm (BST) Virtual virtual Education Webinar - Occupational Stress : Preventing Suffering, Enhancing W... June 10, 2026 11:00AM - 12:00PM virtual Nordic (Denmark, Finland, Norway and Sweden) employment law training June 16, 2026 12.45pm - 4pm (BST) Virtual |